Pages

Wednesday, 27 March 2013

Pipework arrives and starts to be installed

Early in the morning start with delivery of the 4" pipework, the 2" pressure pipe and the steel reinforcement grids arriving on site.

 

By the end of day the initial pipes are being put in place between the pond and the filter house.

 

The old concrete pond waterfall tiers (that used to feed water into the old pond) have now been broken down and placed into the bottom of the filter house floor as hardcore before concrete fill tomorrow.

 